First Church of Christ, Scientist
OVERVIEW
First Church of Christ, Scientist, is located in a historic building that needed updating for modern church needs. First Church contracted Lehman Daman to renovate, changing the layout to improve functionality and updating finishes throughout. .
CHALLENGES
During demolition, L/D uncovered severe underlying structural issues and termite damage that rendered the current building unsafe. New joists and bracings were needed, and an exterior masonry wall had to be rebuilt. This work added unforeseen costs and time to the project, including additional approvals and documentation for the city.
Throughout these challenges, L/D communicated openly with First Church to help them understand the problems and associated costs, including potential cost-saving options, to reduce the financial impact of the additional work.
FEATURES
The church renovation included a reception area, restrooms, meeting areas, and a new reading room. Modern finishes were used, while maintaining the historical character of the building.
Added and expanded restrooms
New exterior storefront and columns matching existing
Client
First Church of Christ, Scientist
Location
Columbus, Ohio
Size
1,992 SF
Delivery
Design/Bid/Build
Completed
2020
Partner
Fasten Design