Columbus Oncology & Hematology

Project Overview
To meet new ventilation/exhaust requirements, Columbus Oncology & Hematology had to expand and update their current system. They chose to complete a concurrent 3,500 SF interior renovation with the needed 1,000 SF addition, adding two new mixing rooms and 7 additional patient care stations.

Design/Build
delivery
Renovation + Addition
project type
4,500 SF
Square feet

Project Challenges
Columbus Oncology & Hematology had to stay operational during construction and could only lose 2 patient care stations at a time (out of 25). To address this, Lehman Daman developed a 10-phase plan over 7 months of construction that kept patients and staff safe. Scheduling a double shift, Lehman Daman worked on the addition during the day and the interior renovation at night.
During the tie-in of the addition to the existing building, a shoring wall was erected that not only supported the structures, but was also built to meet ventilation and air purity requirements and provide sound privacy. For the electrical shutdown, Lehman Daman brought two temporary generators to ensure medication refrigerators kept running.
Project Highlights
- Improve patient care experience
- Add private care space
- Create an in-house Pharmaceutical Suite
- Increase patient care capacity



Medium length section heading
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique.
days ahead of schedule
Lorem ipsum dolor sit amet, consectetur adipiscing elit.
under budget
Lorem ipsum dolor sit amet, consectetur adipiscing elit.